Removal of the existing concrete settling basin located along the downstream side of the Ivanhoe Lake Dam and replacement with a new and longer settling basin.
The work consists of extending the length of the settling basin from 11.7 m to 29.5 m. Work associated with the extension includes new apron walls on the east and west side, steel sheet piling for the end walls, steel soil tieback anchors at the wingwalls and concrete repairs to the existing settling basin.
Ministry of Natural Resources and Forestry of Ontario
$7M
2015-2017
WSP Canada
Foleyet, Ontario, Canada